Contraflow on Queen's Road
Queen's Road is currently one-way for cycling - it would be good to remove this barrier.
This section lists issues - problems on the street network and related matters.
Issues always relate to some geographical location, whether very local or perhaps city-wide.
You can create a new issue using the button on the right.
Listed issues, most recent first:
Martin Lucas-Smith // 1 thread
Queen's Road is currently one-way for cycling - it would be good to remove this barrier.
Created by fh // 1 thread
At busy times of day, it is very difficult for cyclists to turn out of Pembroke Street when turning right onto Trumpington Street. Trumpington street has priority and there are no traffic lights. This creates the following problems:
1) Cyclists turning out of Pembroke Street right onto Trumpington street when there is not enough space/time to do so. This causes a lot of braking and it is common to see a lot of people braking or hear a car horn because of this.
2) Build-ups of cyclists waiting to turn out of Pembroke Street get in the way of buses turning into Pembroke street (as buses need more turning space).
This is particularly bad around 9am.
Created by Andrew Woodward // 0 threads
Can we include the Star and Garter Hill in our list of shared footpaths (actually a footway in this case). Slow-moving cyclists travelling up the hill from Petersham Gate to Richmond Gate have difficulty with fast passing cars on the hill who overtake too closely. This does not occur in the downhill direction because cyclists can travel much faster. The suggested solution is to permit cycling on the footway up the hill only. There are very few pedestrians and in any case the cyclists will necessarily be travelling very slowly so they would cause no problems. The traffic signals at the bottom of the hill would need some alteration to facilitate cyclists crossing from the Petersham Road onto the footway up the hill.
Created by christhebull // 0 threads
The northbound approach to this junction poses a significant hazard for cyclists bearing right onto Gloucester Road, due to the poorly delineated approach and potential conflicts with traffic taking other exits, namely:
1) Cyclists are at risk of being left hooked by vehicles turning left into Zetland Road, and adopting a more central road position may result in the unsettling experience of having faster traffic pass on both sides
2) Cyclists using the central filter lane to access Gloucester Road are at risk of colliding with traffic continuing into Elton Road from the right hand lane - this is because there are no arrow markings painted in the approach lanes, nor any markings in the junction itself to tell road users which lanes to adopt so as to avoid this conflict.
Therefore, I consider it necessary for this junction to have, as a minimum, arrow markings showing which movements are permissible from which approach lane, and markings within the junction to further clarify this. The left hand lane ought to be used by traffic turning left or continuing straight, and the right hand lane for continuing on Gloucester Road only.
If the opportunity for a more substantial rebuild occurs at some point in the future, a wider filter lane should be provided, or some other solution sought.
The other directions of travel at this junction are clearer (apart from the southbound contraflow lane which ends on a pavement, but that is probably less of a road safety issue)
I am fully aware there are proposed changes relating to Gloucester Road under the government's Cycle Safety Fund, but the plans which I have seen do not rectify this particular issue (but if I see the relevant people in the near future, I will raise this issue with them).
Created by Dylan // 1 thread
There is a fairly good cycle lanes from Kingston towards Richmond up until you reach the Richmond Council border where Richmond Road (A307) turns into the Upper Ham Road (A307) and eventually Petersham Road (A307). At traffic lights along this route there are reserved areas for cyclists but along the roads there is nothing to remind drivers that cyclists share the road especially when the road narrows after Sandy Lane through Petersham. The road surface here is terrible and the speed bumps are pointless because some driver sprint between the bumps.
The best solution would be to remove the cyclists from this route altogether by upgrading the Thames Path to create a proper cycle path along the River Thames towards Richmond that currently stops at Teddington Lock. If a cycle/foot bridge linking Ham with Twickenham was built over Eel Pie along this route it would create an obvious link for those want to reach Twickenham.
Martin Lucas-Smith // 3 threads
Huntingdon Road currently has rather narrow cycle lanes, which are unnecessarily so since this is quite a wide road.
There is space here to create really high-quality, direct, cycle infrastructure which retains priority at sideroads and which would encourage new people to start cycling.
Martin Lucas-Smith // 0 threads
There isn't any cycle parking outside this excellent charity centre. A small row of sheffield stands outside the building would be very useful.
Created by John Hall // 0 threads
Cambridge Cycle Brochure
Just a starting point
Format A4
4 to 8 pages
Images and artwork
Audience - Provide solutions for:
school run
commuters - better experience
older people
non cyclists - journey times
improve you neighbourhood
car free households - Zip cars
council officers
village residents
- taxi drivers and our critics
Delivery - with News and Crier?
A test delivery could be used to assess the response to the brochure in terms of new memberships or visits to a web page
Subjects
off road routes to drivers such as along the Cam
3D barcode links to video etc
Segregated cycle routes
Hub and spokes to villages
The CT
West Cambridge Development
Why should new development contain cycle paths?
Why should new buildings have good cycle facilities?
What kind of bike training is available?
Membership form perhaps with a discount for direct debits?
Priority over side roads / platforms / set back crossing
Build it and it will be used e.g. Shelford Path 300k users per annum
Health benefits
Noise pollution
Who pays for roads
Cargo bikes
Go Dutch
Created by Andrew Woodward // 1 thread
Despite the mandatory cyclelanes there are few cyclists who use them, probably due to the high volumes of traffic. The street is wide enough for proper segregation; and is a main route to Kew Riverside school.
Created by Andrew Woodward // 0 threads
Cyclists crossing the junction on the road (not the pavement) going north are frequently squeezed by the pinch point created by the central pedestrian crossing refuge at the mouth of the A205 and junction with A316
Created by Andrew Woodward // 1 thread
This stretch of Clifford Ave joins LCN37 to the A316 cycle track and to LCN 33 up to Kew.
However, it is usually very congested, there are often large trucks; and there is no form of protection for cyclists on this stretch of road.
Created by Andrew Woodward // 1 thread
South Worple Way is signposted as part of LCN 37; but the western end of it is blocked off with this obstruction; which leaves only a very narrow gap for bikes to get through. Could you get a cargo bike or a trailer through there?
Created by Andrew Woodward // 0 threads
Doing the school run on bikes - with hiviz, helmets and cycling on the pavement. Queens Road, Richmond, northbound. Cyclists feel vulnerable due to high traffic volumes. There is a wide pavement and wide road here; with enough space to create a dedicated cyclepath.
Created by Andrew Woodward // 1 thread
This dad with kids in a trailer clearly doesn't feel safe enough to use the bike lane so he cycles on the pavement. Probably because he's on the way to one of the 7 schools or nurseries near to this route; and the cars are doing 40mph on that nice wide road. This is a regular sight on this route.
Created by Andrew Woodward // 0 threads
Despite the cycle lanes being mandatory along this stretch the road layout is such that vehicles frequently intrude into the cyclelane - as this bus did.
White paint does not work on this stretch and some other segregation method is needed -eg a kerb; vertical posts or similar.
Created by Andrew Woodward // 0 threads
The A316 is interrupted at Manor Circus; requiring a dismount to walk around the roundabout before you can continue again East-West.
Created by Andrew Woodward // 0 threads
Street signage causes unacceptably narrowing of the cyclepath at this point.
Created by Andrew Woodward // 1 thread
I have serious concerns about the safety of this portion of the bike path; arising from its recent re-design. Recently my 10 year old son was in a very close “near-miss” with a car turning off the A316 into Bicester Road; and I believe many more similar incidents are likely occurring. Eventually someone will be seriously hurt or killed on it.
However, the improvement in the track leads cyclists to feel more confident in using it – giving a false sense of security.
In particular:
• The segregated track makes it particularly appealing for inexperienced and more vulnerable cyclists (such as kids).
• This track design leads to an increase in the cyclists speed.
• The smooth/quick nature of the track leads inexperienced cyclists to believe that THEY HAVE RIGHT OF WAY across side roads.
• There are no markings on the roads to tell drivers coming in or out of side roads that cyclists could be on the track crossing their path.
• There is a particular challenge for EASTBOUND cyclists.
To avoid stopping at every side road, when on the track travelling Eastbound (as per red arrow on photo) approaching roads such as Bicester road, the cyclist has to simultaneously
(a) check to their FRONT/LEFT side to see if a car is exiting the side road
(b) check BEHIND them on their REAR/ RIGHT hand side to see if a car is about to swing off the A316 into the side road (usually at speed) - (as per orange arrow on photo).
This is a hard combination to perform – looking 180 degrees opposite directions at the same time. If you are an inexperienced cyclist, on an apparently safe track, it is very likely that you will not realise you have to be this vigilant and not check adequately for cars.
Hence, my boy rode across Bicester road from the east and was very nearly hit by a car turning off the A316.
(Note that travelling from the west is somewhat easier as both the vehicles turning in from the A316 and those turning out from the side roads are in your front field of vision).
My suggestions for improving this situation are:
(1) Clearly mark the bike track across the side roads so cars are aware there are cyclists approaching from the side.
(2) Ideally, give cyclists priority across the side roads; so making cars slow to a halt and making it more intuitive for cyclists.
(3) To facilitate this, would require some stopping space for traffic coming on/off the A316 to after the bike track crossing
At roads such as Bicester road the bike track could be curved to the south by about 2m before crossing the side road – this curve in the track would
(a) naturally slow cyclists down as they approach the side road
(b) would provide vehicles moving onto the A316 a decent gap so they can separate the concerns of first negotiating the bike track then focus on getting on the A316;
(c) for vehicles coming off the A316 the additional space would give them space to stop and give way to cyclists.
Created by Mark A // 1 thread
A dropped kerb at this point would improve the route that people can take to cycle between Bear Flat and the city centre - making it easier to use Calton Gardens to avoid the section of footpath on the alternative via Holloway and St Marks Church.
Created by Andrew Woodward // 0 threads
There's plenty of shops on White Hart Lane but the only bike parking is right at the northern end. There is room for more bike stands near the shops at the southern end opposite Westfields Avenue.
Created by DavidT // 2 threads
The current layout of the pedestrian crossing at the junction of Winchester road and Vermont close forces cyclists out of the cycle lane and into the flow of traffic. This is a risky maneuver and relies on the patience of the car driver behind the cyclist. A possible solution would be to be extend the cycle lane through the chicane, with give way markings so that pedestrians have right of way.
Martin Lucas-Smith // 1 thread
Anglia Ruskin are developing their new Faculty of Health, Social Care and Education here. They are required to undertake amendments to the junction here. Can this be improved for cycling?
Created by Sam Saunders // 1 thread
Busy Ashton Road (a 20 mph road from the A3029) bends eastward into the commercial area of North Street, close to a well-used park. On the bend, immediately adjacent to a park entrance, Frayne Street brings one-way traffic from the north west, and allows cycles to travel in the opposite direction towards Cumberland Basin. Coronation Road has two way traffic on the north east side.
A recently installed calming measure has narrowed the road on the bend, as shown in the picture. The irregular shape of the road that results has made the turn into Coronation Road awkward for cyclists and, as can be seen from the lower half of the picture, some cyclists take ad hoc routes to avoid the complication. Buses and large lorries also use the route into North Street and most vehicles take the bend at about 30 mph, despite the speed restriction.
As a route for cyclists, there could be a continuous segregated lane alongside the park (perhaps shaving a metre from the park itself, crossing Frayne Road with priority and following Coronation Road eastbound. A large number of school children use the route along the park every day but only a very few use a bicycle.
Created by Eric Booth // 2 threads
Prince St bridge is an anarchic pigs ear. I like pigs and fond of a bit of anarchy but it's getting beyond a joke. Of course it will all be sorted out properly in due course but we could live with this for years. Here's a quick fix:
SOUTH
1. Move south vehicle stop line back 10m behind tramlines
2. Remove all bollards unless one or two kept in line with centre of bridge with arrows right for cars
3. Widen cycle lane from bridge to Festival way turn so suitable for 2-way cycling.
4. Put in Give Way painted line at an angle running from enlarged cycle lane to centre line so southbound cyclists alerted to need to filter across traffic.
NORTH
1. Remove all bollards
2. Widen cycle lane for 2 way cycling all the way up to the traffic lights with The Grove.
3. Remove 5 bollards on each side of north bound traffic light along with the two set back
4. Paint cycle lane passing behind light and then back onto carriageway making it nice and clear that it's an option for cyclists when lights red or they can carry on (as most will, no worse than now but at least it will be clear that they can treat these as 'give way')
5. There will need to be 'give way' paint to make clear that pedestrians have right of way on the by-pass.
Yes it's muddled but less so than now and makes the desire lines easier. It's also a cheap paint based fix pending the proper job.
Created by Sam Saunders // 1 thread
Cycling North along Westbury Road (A4018) on a shared-use pathway beside the main carriageway there is a sign to "Westbury Park Shops". It is about 50 yards before the Parry's Lane roundabout and indicates a right turn ahead for cyclists and pedestrians. It has been added to a larger sign that reads "New Road Layout".
In practice, on arrival at the roundabout there is no indication before, on or after the roundabout as to where cyclists should go next. A zebra crossing before the roundabout offers a dismounted route to the other side of the road, but there is no indication of which direction to take thereafter. There are 4 roads to chose from, Westbury Park, Etloe Road, North View and Downs Park West but none of them seem to offer shops. There are two ambiguous cycle lane markings on the entrance to Westbury Park and "NO CYCLING" is painted on one footpath.
The problem, in a nutshell, is one that recurs all over Bristol: if you don't already know the way a first encouraging sign gives expectations that are not followed through. A route that had been indicated as a cycle route (with the cycle symbol) at its origin is left to chance and guesswork. The effect on cycling is to increase uncertainty and unpredictability. Each cyclist is obliged to make guesses about how to use a junction or follow a route. An association of cycling with expert and arcane knowledge is reinforced. Many routes (including this one) could be improved with a few additional signs or road markings and their use by casual or less well-informed cyclists could be encouraged.
This map shows all issues, whether points, routes, or areas:
The most popular issues, based on the number of votes:
Created by Hester Wells // 1 thread
There is a campaign for a cycle route between Bar Hill and Cambridge, also connecting Dry Drayton, Madingley and Coton to North-West Cambridge.
Currently cycle provision for these villages is poor. Bar Hill has lower rates of cycling than other villages that are closer to Cambridge.
The campaign site is: http://www.bhddmadcycle.com/
Created by David Green // 1 thread
My employer is planning to relocate from central cambridge to the Cambridge Business Park (near Waterbeach). There is currently no decent cycle (or footpath!) access to this business park which avoids riding along the A10. I am a confident cyclist but I am not looking forward to riding to work along sections of the A10.
Are there any plans for cycle route construction which the campaign can, perhaps, help accelerate?
Created by Sarah Wood // 0 threads
This contraflow infrastructure is hazardous for several reasons: the path is very narrow - realistically around 0.5m wide, the cyclists is riding in the gutter, at risk of being doored and catching wing mirrors. What caught me out was a vehicle travelling North and turned right to access an entrance. Our sight lines were blocked by parked vehicles in parking bays to the right of the cycle path. Until this situation is addressed cyclists will continue to be vulnerable along this section of the road.
Created by Simon Nuttall // 19 threads
The Reach Fair ride takes place on the early Bank Holiday Monday (May Day) in May.
The web page for it is:
http://www.camcycle.org.uk/events/rides/
The planning overview is summarised:
http://www.camcycle.org.uk/events/rides/timeline.html
I've created this issue to help plan this event.
Created by HVS // 2 threads
The A41 ring road cuts across a useful quiet route north-west out of Chester, which is an alternative to the traffic-free Greenway (which is unlit, and slippery in icy conditions). Crossing the A41 during busy periods - e.g. when commuting at rush-hour - can be a slow and potentially very dangerous process, especially after dark. A better crossing for cyclists and pedestrians, or a lower speed limit on the A41 (or both), would be very helpful here.
[Original version of map was wrong; I've now updated it.]
As the bridleway crosses Milton Road, it swaps sides of the busway, so most pedestrians and cyclists want to cross diagonally. However the toucan crossing only protects people crossing Milton Road. It doesn't stop busway traffic.
This is confusing and dangerous. When the road traffic stops at red lights, and the Toucan crossing turns green, it feels very safe to cross the busway. Yet buses can come from three directions (busway west, busway east, Milton Road south) at speeds of 30 mph.
Cyclists in particular are tempted to cross diagonally from north west to south east. Last week I saw a near accident.
Created by Sarah Wood // 0 threads
There are several pedestrian refuges along the road particularly at the western end of the road. The refuges cause a pinch point for cyclists. The road marking confuse priorities between those using the on road cycle path and other traffic.
Created by Andrew Woodward // 0 threads
Cyclist coming from the river come up Friars Lane exit and have to currently route right round Richmond Green because it is one way. Many do not and simply cycle across the green. The path across the green should be formally opened up to cyclists - as a share path with pedestrian priority - or a seperate track provided along the south side of Richmond Green.
Created by Kevin Ablitt // 1 thread
Motorised vehicles currently use the rat run through Milner Street to avoid the fraffic lights at Grove Lane/ St Helens St.
This is part of NCN 41 , any extra traffic passing through here detracts from the cycling experience and is negative for residents.
Cyclist comments are needed now !
Created by Eric Booth // 2 threads
Prince St bridge is an anarchic pigs ear. I like pigs and fond of a bit of anarchy but it's getting beyond a joke. Of course it will all be sorted out properly in due course but we could live with this for years. Here's a quick fix:
SOUTH
1. Move south vehicle stop line back 10m behind tramlines
2. Remove all bollards unless one or two kept in line with centre of bridge with arrows right for cars
3. Widen cycle lane from bridge to Festival way turn so suitable for 2-way cycling.
4. Put in Give Way painted line at an angle running from enlarged cycle lane to centre line so southbound cyclists alerted to need to filter across traffic.
NORTH
1. Remove all bollards
2. Widen cycle lane for 2 way cycling all the way up to the traffic lights with The Grove.
3. Remove 5 bollards on each side of north bound traffic light along with the two set back
4. Paint cycle lane passing behind light and then back onto carriageway making it nice and clear that it's an option for cyclists when lights red or they can carry on (as most will, no worse than now but at least it will be clear that they can treat these as 'give way')
5. There will need to be 'give way' paint to make clear that pedestrians have right of way on the by-pass.
Yes it's muddled but less so than now and makes the desire lines easier. It's also a cheap paint based fix pending the proper job.
Created by Rosie Downes // 5 threads
Transport for London's public consultation on Cycle Superhighway 1 is open from 16 February to 29 March. The LCC office has set up this thread to facilitate discussion of the proposals.
Created by WildNorthlands // 1 thread
Brook Hill roundabout is a major barrier for cyclists in West Sheffield. The traffic is fast and as it is a three-lane spiral roundabout with the exit roads (except Bolsover St) having two lanes there is a lot of lane-switching by motorists. This makes the risk of a collision very high, and for less experienced cyclists it is simply a no-go area.
Many of the buildings adjacent to the roundabout belong to the University, and have been built up to the curtilage, so there is no space to expand the pavements and make them shared use.
One alternative for cyclists coming from the Walkley/Crookes area via Bolsover St is to use Tower Court, but this area can be very congested when the University is in session, with several thousand students using the Arts Tower and Library.
The council has signed an alternative route via Weston St and the Netherthorpe Rd tram subway, but this involves a drop in height of about 100 metres and subsequent climb up again, plus the negotiation of access barriers in the subway, so is not really sensible.
Meanwhile on Upper Hanover Way, a cycle crossing was severed when the tramway was installed, although cyclists still use the crossing. A proposed alternative crossing is stalled as it is too expensive.
What can be done about this knotty problem?
Martin Lucas-Smith // 1 thread
The permeability gate between Hooper Street and Kingston Street is obstructive as it only allows passage in one direction at a time.
Given the ever-increasing amount of cycling in areas like this, it's time to get this replaced with a simple bollard arrangement that would allow two-way passage whilst still enable the emergency services to unlock for access in an emergency.
Created by Andrew Woodward // 1 thread
I have serious concerns about the safety of this portion of the bike path; arising from its recent re-design. Recently my 10 year old son was in a very close “near-miss” with a car turning off the A316 into Bicester Road; and I believe many more similar incidents are likely occurring. Eventually someone will be seriously hurt or killed on it.
However, the improvement in the track leads cyclists to feel more confident in using it – giving a false sense of security.
In particular:
• The segregated track makes it particularly appealing for inexperienced and more vulnerable cyclists (such as kids).
• This track design leads to an increase in the cyclists speed.
• The smooth/quick nature of the track leads inexperienced cyclists to believe that THEY HAVE RIGHT OF WAY across side roads.
• There are no markings on the roads to tell drivers coming in or out of side roads that cyclists could be on the track crossing their path.
• There is a particular challenge for EASTBOUND cyclists.
To avoid stopping at every side road, when on the track travelling Eastbound (as per red arrow on photo) approaching roads such as Bicester road, the cyclist has to simultaneously
(a) check to their FRONT/LEFT side to see if a car is exiting the side road
(b) check BEHIND them on their REAR/ RIGHT hand side to see if a car is about to swing off the A316 into the side road (usually at speed) - (as per orange arrow on photo).
This is a hard combination to perform – looking 180 degrees opposite directions at the same time. If you are an inexperienced cyclist, on an apparently safe track, it is very likely that you will not realise you have to be this vigilant and not check adequately for cars.
Hence, my boy rode across Bicester road from the east and was very nearly hit by a car turning off the A316.
(Note that travelling from the west is somewhat easier as both the vehicles turning in from the A316 and those turning out from the side roads are in your front field of vision).
My suggestions for improving this situation are:
(1) Clearly mark the bike track across the side roads so cars are aware there are cyclists approaching from the side.
(2) Ideally, give cyclists priority across the side roads; so making cars slow to a halt and making it more intuitive for cyclists.
(3) To facilitate this, would require some stopping space for traffic coming on/off the A316 to after the bike track crossing
At roads such as Bicester road the bike track could be curved to the south by about 2m before crossing the side road – this curve in the track would
(a) naturally slow cyclists down as they approach the side road
(b) would provide vehicles moving onto the A316 a decent gap so they can separate the concerns of first negotiating the bike track then focus on getting on the A316;
(c) for vehicles coming off the A316 the additional space would give them space to stop and give way to cyclists.
Created by Rosalind Lund // 1 thread
further to the piece in newsletter 128, I wonder if any thought has been given to the difficulty of turning right into Emmanuel Street if you are coming towards the town centre from St Andrew's Street? We go fairly often to the Arts Cinema and this is the obvious way for us to go home, but it is impossible to turn right on the correct side of the bollard at present as it is designed only for left turning cycles coming out of town. There is, however, nothing to suggest that such a right turn is illegal.
Created by Shaun McDonald // 0 threads
The entrance to Dock Street should be turned into a continuous footway with pedestrian and cyclist priority over turning vehicles akin to this Danish junction: http://www.youtube.com/watch?v=QcnmLU1ClTo
This would improve sight lines for pedestrians too as the dropped kerbs are away from the junction, and it would also go with the pedestrian desire line as many tend to cross closer to the junction than the dropped kerbs. It would also slow down the vehicles entering the narrow street.
Martin Lucas-Smith // 1 thread
There's a very poor dogleg right-angle with barriers at the entrance/exit from the West Cambridge site to Clerk Maxwell Road.
This should be turned into a wide splay with good visibility.
Over the past couple of years of regularly cycling between Waterbeach and Cambridge on NCN11 I have noticed that the path between Waterbeach and Baits Bite Lock is in really bad repair and is getting gradually worse. I have been in touch with the council to ask them to repair it, and they told me that as far as they are concerned the path is only a footpath, and they have no obligation to maintain it to a standard suitable for bikes. Sustrans tells me they have no responsibility for maintaining that section of the route, and that the council should be responsible for it.
It seems absurd to allow the path to fall into total disrepair, but at the moment it doesn't seem like anyone recognises any obligation for its upkeep.
I am happy to go out occasionally with some secateurs and chop off the more annoying bits of greenery, but the path needs resurfacing and that feels a bit beyond me!
Does anyone have any experience with this sort of problem? Have they come across it on other sections of the NCN?
Martin Lucas-Smith // 11 threads
Major planning application here - c. 10,000 homes
Created by Ned Harrison // 1 thread
Holywells Park has a section of cycle route 51 running through it, linking South East Ipswich to the centre with a pleasant and safe route down to the waterfront.
During Winter, the park is closed at dusk, sometimes as early as 4, meaning that just when the roads are most dangerous (dark and wet) cyclists are forced onto steep and busy routes either along Cliff Lane or up Bishops Hill.
The closures are largely at the request of the Park Friends group. I've spoken to them, and their concerns seem to be largely about what might go on after dark. It's not clear that there is any evidence for this, nor that the current situation of locking the main gates but leaving others would do anything to deter misbehaviour.
Keeping it open as a cycle route would ensure a legitimate presence in the park, and help provide less confident cyclists in the area with a safe route to and from town.
I'd propose either locking later, or for a trial period leaving the park unlocked.
Created by Shaun McDonald // 1 thread
Many cyclists won't cycle to Harwich International from the Ipswich direction due to the roads. There really should be a high quality cycle route for this to continue the cycle journey from The Netherlands, where you can ride of the ferry and on to quality cycle infrastructure. The fact people choose the train is not a good sign.
This issue is the overall goal, and needs to be broken down into smaller sub issues of smaller more specific projects or improvements that can work towards this goal.
Meeting with Leeds City Council to discuss possible remedial works due to high casualty rates.
Created by PurpleSue // 2 threads
I watch in wonder and amazement as the new cycle lane alongside the A41 from Mostyn lights to the zoo is completed - with lamposts in th emiddle of the path - not to mention a three legged road sign which I am sure will make passage impossible.
I will investigate more and take photos....
Created by chdot // 1 thread
Longstanding issue about 'optimum' design, particularly to reduce conflict caused by vehicles turning from Teviot Pl due to signal phases.
Created by JonC // 0 threads
Our club (South Herts CTC) had to cross the A505 to get back into Hertfordshire on Sunday and we took a route between Litlington and Therfield which involved 500 m along the A505 and a right turn at the roundabout west of Royston.
I was quite surprised there was no cycle route to help cyclists here. It was a Sunday so at least there were fewer heavy vehicles than normal, but the speed of some cars coming up behind made it tricky to change lanes on a bike when turning right at the roundabout.
Since then I have studied other ways of crossing the A505 (using Google Streetview) and can't find any easy crossing points near Royston. I see it is the boundary between Hertfordshire and Cambridgeshire, which complicates matters (although it looks like the A505 road is in Herts).
To the east, I've used the B1368 crossing at Flint Cross, which is also a nightmare. To the west the crossing at Slip End does at least have a central refuge. It seems little or no thought was given to cyclists when the A505 was constructed.